Project Scope & Timeline

The $6.2 million project scope includes:



  • Building the new Early Childhood Center with twice the classroom space of the current center,
  • Building four classrooms in the new center to move the current Kindergarten through Second grades,
  • Building the shell on the 2nd story of the new center with enough room for an additional 5 future classrooms,
  • Building a large multi-purpose room in the new center for indoor play area, worship, etc.,
  • Building a new Bus Garage/Storage/Car Care building,
  • Building a 105 space parking lot,
  • Purchasing Hickory and Morin streets,
  • Completing upgrades to current sanctuary including lighting and electrical,
  • Remodeling current facilities for new Youth, Music, Meeting, and Nursery rooms.

The project timeline is:


·         Reformation Sunday 2007 – Groundbreaking


·         Fall 2007 – Youth Rooms


·         December 2007 – Sanctuary Lighting and Electrical


·         December 2007 – Bus Garage/Storage/Car Care Building


·         November 2008 – New Early Childhood Center


·         December 2008 – Parking Lot


·         January 2009 – Dedication Sunday